Start/Stop Service
New Service Applications
To establish electric service with Palmetto Electric Cooperative, the consumer must apply for membership. In addition to the fees shown below, a deposit may also be required for service to be connected. When your account is created, you will receive an email with the total amount due on your new account, including the deposit amount and the membership fee, if applicable. The deposit is due before electric service will be activated. To obtain service for a new structure, proper county permits and inspections are required before power is connected. The procedure for obtaining temporary service, such as power for building a house, is the same as applying for new service. A valid county permit is also required.
-
Membership Fee: $5.00
-
Processing Fee: $20.00
Residential Application
Please be aware of the following items regarding residential applications:
-
In order to complete your application online, you must provide all information requested on the application. You will not be able to submit the application if any of the required fields are left blank.
-
An application must be completed for EVERY meter that needs service.
-
A deposit may be required for electric service to be connected. The deposit amount is based on a risk factor analysis.
-
Applications will be reviewed during normal business hours (Monday - Friday, 8 a.m.- 5 p.m., excluding holidays), and you will be contacted to complete the application process.
Commercial Application
Please be aware of the following items regarding commercial applications:
-
In order to complete your application online, you must provide all information requested on the application. You will not be able to submit the application if any of the required fields are left blank.
-
A deposit WILL BE REQUIRED for electric service to be connected. The deposit amount is based on a two-month average bill at the service location.
-
Applications will be reviewed during normal business hours (Monday - Friday, 8 a.m.- 5 p.m., excluding holidays), and you will be contacted to complete the application process.
New Construction Application
Please be aware of the following items regarding new construction applications:
-
In order to complete your application online, you must provide all information requested on the application. You will not be able to submit the application if any of the required fields are left blank.
-
A deposit on new members for temporary service.
-
To obtain service for a new structure, proper county permits and inspections are required before power is connected.
-
The procedure for obtaining temporary service, such as power for building a house, is the same as applying for new service. A valid county permit is also required.
-
Applications will be reviewed during normal business hours (Monday - Friday, 8 a.m.- 5 p.m., excluding holidays), and you will be contacted to complete the application process.
Disconnect Service
To disconnect service, please login to your MyEnergy Online account or contact your local district office.